Title: AC Power Flow-Based Co-Optimization for Integrated Generation and Transmission Network Expansion Planning
Authors: Torres Contreras, Santiago Patricio
metadata.dc.ucuenca.correspondencia: Torres Contreras, Santiago Patricio, santiago.torres@ucuenca.edu.ec
Keywords: Transmission Expansion Planning
Co-optimization
Generation Expansion Planning
Integrated planning
metadata.dc.ucuenca.areaconocimientofrascatiamplio: 2. Ingeniería y Tecnología
metadata.dc.ucuenca.areaconocimientofrascatidetallado: 2.2.1 Ingeniería Eléctrica y Electrónica
metadata.dc.ucuenca.areaconocimientofrascatiespecifico: 2.2 Ingenierias Eléctrica, Electrónica e Información
metadata.dc.ucuenca.areaconocimientounescoamplio: 07 - Ingeniería, Industria y Construcción
metadata.dc.ucuenca.areaconocimientounescodetallado: 0713 - Electricidad y Energia
metadata.dc.ucuenca.areaconocimientounescoespecifico: 071 - Ingeniería y Profesiones Afines
Issue Date: 2024
metadata.dc.ucuenca.volumen: Volumen 0, número 0
metadata.dc.source: IEEE Power and Energy Society General Meeting
metadata.dc.identifier.doi: 10.1109/PESGM51994.2024.10689001
Publisher: IEEE
metadata.dc.description.city: 
Seattle
metadata.dc.type: ARTÍCULO DE CONFERENCIA
Abstract: 
The integrated Generation and Transmission Network Expansion Planning (GTNEP) models have been developed to enable simultaneous investment decisions that consider both investment and operational components. In this research, a new methodology to assess the GTNEP is proposed, which takes into account the integrated planning of new generation power plants, transmission lines, reactive power allocation, and network power losses. To address the GTNEP, the operational problem is formulated using the AC optimal power flow, providing more realistic solutions. As a solution method, the Iterated Greedy Algorithm (IGA), and a hybridization of differential evolution with the tabu search (DE-TS) meta-heuristic were implemented. The proposed approach was tested using the 6-bus Garver test system. The results demonstrate that more cost-effective and realistic expansion plans are found with integrated AC-GTNEP compared to the sequential approach of first solving Generation Expansion Planning (GEP), and then Transmission Network Expansion Planning (TNEP).
URI: https://dspace.ucuenca.edu.ec/handle/123456789/46219
https://www.scopus.com/record/display.uri?eid=2-s2.0-85207440221&doi=10.1109%2fPESGM51994.2024.10689001&origin=inward&txGid=810de7e9b4f8955102fc50930dcdd7be
metadata.dc.ucuenca.urifuente: https://pes-gm.org/seattle-2024/program/
ISBN: 979-835038183-2
ISSN: 1944-9925
Appears in Collections:Artículos

Files in This Item:
File SizeFormat 
documento.pdf258.38 kBAdobe PDFView/Open


This item is protected by original copyright



Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.

 

Centro de Documentacion Regional "Juan Bautista Vázquez"

Biblioteca Campus Central Biblioteca Campus Salud Biblioteca Campus Yanuncay
Av. 12 de Abril y Calle Agustín Cueva, Telf: 4051000 Ext. 1311, 1312, 1313, 1314. Horario de atención: Lunes-Viernes: 07H00-21H00. Sábados: 08H00-12H00 Av. El Paraíso 3-52, detrás del Hospital Regional "Vicente Corral Moscoso", Telf: 4051000 Ext. 3144. Horario de atención: Lunes-Viernes: 07H00-19H00 Av. 12 de Octubre y Diego de Tapia, antiguo Colegio Orientalista, Telf: 4051000 Ext. 3535 2810706 Ext. 116. Horario de atención: Lunes-Viernes: 07H30-19H00