Título : Optimal subtransmission switching using a reliability simulation-based multi-objective optimization model
Autor: Zambrano Asanza, Sergio Patricio
Lema Guaman, Edwin Marcelo
Franco, John Fredy
Banegas Dutan, Stalin Fernando
Proaño Barros, Tatiana Michelle
Palabras clave : NSGA-II optimal switching
Subtransmission system
Reliability
Distribution planning
Área de conocimiento FRASCATI amplio: 2. Ingeniería y Tecnología
Área de conocimiento FRASCATI detallado: 2.2.1 Ingeniería Eléctrica y Electrónica
Área de conocimiento FRASCATI específico: 2.2 Ingenierias Eléctrica, Electrónica e Información
Área de conocimiento UNESCO amplio: 07 - Ingeniería, Industria y Construcción
ÁArea de conocimiento UNESCO detallado: 0713 - Electricidad y Energia
Área de conocimiento UNESCO específico: 071 - Ingeniería y Profesiones Afines
Fecha de publicación : 2022
Volumen: Volumen 210
Fuente: Electric Power Systems Research
metadata.dc.identifier.doi: 10.1016/j.epsr.2022.108068
Tipo: ARTÍCULO
Abstract: 
The growth of subtransmission network aims at satisfying load growth, maintaining a contingency level, and providing a high quality and reliable electricity service. Utilities direct the investments to reinforce this system and thus a meshed network with multiple-point feeding to the transmission system arises. At this point, an efficient alternative to achieve these objectives is to carry out a diagnosis of the network architecture and, taking advantage of the switching capability, to plan the switching of the subtransmission lines. An optimal subtransmission switching approach is proposed based on constrained multi-objective optimization that deals with energy losses and reliability, in addition to using information on the characteristics of loads and generation. A simulation-based optimization framework is constructed using the non-dominated genetic classification algorithm NSGA-II in the optimization phase and reliability assessment during simulation phase. As a result, a set of non-dominated solutions approximating the Pareto front is obtained, which allows the planner to make decisions based on its priorities and needs. The performance of the proposal is assessed with a real subtransmission system of an Ecuadorian power utility. This approach to the operational planning of a meshed subtransmission network constitutes a powerful decision-making tool that could be adopted by distribution utilities.
URI : http://dspace.ucuenca.edu.ec/handle/123456789/40841
https://www.scopus.com/record/display.uri?eid=2-s2.0-85130379388&doi=10.1016%2fj.epsr.2022.108068&origin=inward&txGid=2ce6dab19966223120f5a42e8df91777
URI Fuente: https://www.sciencedirect.com/journal/electric-power-systems-research/vol/210/suppl/C
ISSN : 0378-7796
Aparece en las colecciones: Artículos

Ficheros en este ítem:
Fichero Tamaño Formato  
documento.pdf3.02 MBAdobe PDFVisualizar/Abrir


Este ítem está protegido por copyright original



Los ítems de DSpace están protegidos por copyright, con todos los derechos reservados, a menos que se indique lo contrario.

 

Centro de Documentacion Regional "Juan Bautista Vázquez"

Biblioteca Campus Central Biblioteca Campus Salud Biblioteca Campus Yanuncay
Av. 12 de Abril y Calle Agustín Cueva, Telf: 4051000 Ext. 1311, 1312, 1313, 1314. Horario de atención: Lunes-Viernes: 07H00-21H00. Sábados: 08H00-12H00 Av. El Paraíso 3-52, detrás del Hospital Regional "Vicente Corral Moscoso", Telf: 4051000 Ext. 3144. Horario de atención: Lunes-Viernes: 07H00-19H00 Av. 12 de Octubre y Diego de Tapia, antiguo Colegio Orientalista, Telf: 4051000 Ext. 3535 2810706 Ext. 116. Horario de atención: Lunes-Viernes: 07H30-19H00